Corrective Action
Corrective Action is an improvement or series of improvements to an Organization’s business processes and procedures to correct the root cause(s) of a non conformance and to prevent their recurrence.
Corrective Action is an improvement or series of improvements to an Organization’s business processes and procedures to correct the root cause(s) of a non conformance and to prevent their recurrence.
Calling all Nuclear Engineers and Scientists! Join PTAG this fall for the online course through Ontario Tech University on Best Practices in Project Management.
Non-conformances are problems that have been found and need be addressed. They can be found anywhere – in a product, in service delivery, in work execution, in a process or even in the Quality Management System itself.
Company – Joint Venture, Oil Producer and Chemical Company
Industry – Advanced Chemical Refining
Category – Construction Management
Project Budget – $215M
Goal – Recover Schedule, Minimize Cost Over Runs, Improve Safety and Quality, Improve QA/QC, Develop Risk Mitigation Plans.
Obstacles – Existing supplier contracts lacked appropriate incentives and disincentives. Full craft employment issues in the region. Site construction culture not contusive to injury prevention, inexperienced and understaffed JV project management. Undersized steam plant to accommodate new capacity.
Solutions – Added Construction management teams between JV team and suppliers. Implements new Safety Plan, Re-Baseline of Schedule and Cost, Implementation of Project Controls including Cost/Schedule curves, comprehensive Dashboard and weekly reporting.
Results – Improved Safety results to lower than industry averages. Recovery of Schedule by two months, Reduced RFI’s and NCR’s, Improved craft productivity, Daily Progressing Accurate Cost Forecasting.
Improve all aspects of Construction Management to Deliver Project
Management of Change to Achieve Compliance
Challenges to meeting the goals of the project:
PTAG’s Team of On-Site Subject Matter Experts Delivered and Implemented the Program
Reorganized the Joint Venture project management approach, establishing an experienced and expanded construction management team to replace supplement/replace personnel from the JV members. Six-person CM Team included Senior CM, Planner, Cost Engineer, Quality Manager, Safety Manager, Contracts/Procurement Manager
Reorganized the reporting, planning and meeting structures for Site, E&P, GC and Subcontractors to report to and integrate with the new CM Team to improve construction planning, execution, quality and safety.
Implemented a new GC led safety program based on “Beyond Zero Accident Techniques” with full site training. New experienced CM Team Safety Manager integrated Site and GC safety teams into a single team. JV and GC senior management attended weekly safety meetings. Improved the focus on behavior, hazard awareness, safety planning and supervision as key areas for continual improvement. Increased safety supervision.
Developed new manpower plan to attract additional craft including adding a second shift to help recover schedule
Using progress to date, updated engineering and procurement schedules, established a new baseline for project schedule and budget.
Developed a weekly reporting structure based on a one-page Dashboard that provides at a glance information on Highlights, Safety, Milestones, Construction, Engineering, Project Services, Quality, Risk and Commissioning/Start-up Readiness. Details for each Key Result Area contained in eight-page attachment. Trained all site management and supervision on new processes and required reporting
Established Risk Register with weekly updates included in the weekly Dashboard and Report
SMEs Delivered, Implemented, Administered and Monitored the Program
SMEs Delivered and Implemented the Program
PTAG’s Advisory TEAM performed a two-week assessed reviewing contract documents, execution plans, supplier agreements, procurement schedules project, organization structure, estimates, budgets, schedules, craft productivity and safety plans and performance. We established that root cause to the poor safety, quality, schedule and cost adherence was an understaffed and inexperienced owners team, combined with weak supplier agreements, poorly developed scope, estimate and schedule with the Engineers and GC along with immature project procurement and project controls.
The solution proposed and accepted was an experienced 6-person CM team located at the project site with direct links to the JV Team for timely decision making to develop and implement a recovery plan. The CM Team implemented a recover plan starting with a new baseline for project budget and schedule, established a safe working environment, focused on engineering deliverables, procurement, quality and improving craft productivity.
“We now have visibility and confidence in the project’s schedule and budget”
Owner Senior Executive
PTAG provides leading firms in the Power, Oil & Gas, Petrochemical, Mining, and Capital Infrastructure markets with qualified People, efficient Business Processes, and Information Management Systems that ensure consistently successful delivery and efficient operation of major capital projects.
Company – Original Equipment Manufacturer – OEM
Industry – Electrical Generation
Category – Equipment Supply and Installation
Project Budget – Multiple Projects
Goal – Recovery action plan to improve quality performance to re-assure Owner that the OEM can be trusted to provide a reliable and warranted product
Obstacles – Global company with manufacturing facilities in numerous countries supplying equipment
Solutions – Conducted an internal analysis of both historical and active projects and audited their Quality Program. Recommended and supported the implementation of accepted actions items to address gaps in their Quality and Training programs.
Results – Improved quality results to assure Owner that the company can be trusted to reliably deliver on its commitments and jointly develop an “owner specific” approach aimed at improving customer satisfaction.
Improve Quality and Restore Owners Confidence
Management of Change to improve quality performance
Challenges to meeting the goals of the project:
PTAG’s Team of Subject Matter Experts Delivered and Implemented the Program
Original Equipment Supplier (OEM) was constrained from participating in any proposal submissions due to performance related issues until it was demonstrated to the Owner that existing technical deficiencies were addressed, and Quality program was enhanced.
The team developed and implemented the processes and procedural changes required for Quality improvement to their existing QA/QC program and identified areas for improved training opportunities. QA/QC Best Practices were deployed throughout the organization.
Mitigation plan was developed to limit the schedule impact of some of the on-going projects and to meet delivery requirements of future projects.
Identified the need for increased communication and provided a solution plan for a better communication structure to be applied at all levels of the OEM organization
Enhanced risk identification and control process were executed during the detail design, through manufacturing and installation phases
Constructed an internal audit process identifying findings and KPI measurements for improvement throughout all global facilities and on-site project locations. Team coached OEM project staff to identify and understand the planning techniques to mitigate the impacts of Non-Conformances
SMEs Delivered, Implemented, Administered and Monitored the Program
SMEs Delivered and Implemented the Program
PTAG’s TEAM of 3 SMEs identified Quality Management Best Practices, delivered the expertise needed to modernize the organizations Quality Management program which resulted in a significant reductions in NCR’s and restored the CONFIDENCE of the Owner and its representatives
Owner was presented the OEMs action plan to enhance performance, improve quality, productivity, safety and eliminate rework occurrences
OEM welcomed suggested corrective actions from both the PTAG SME’s and Owner representatives to ensure the OEM remained the supplier of choice
Step 1: Define and Implement Your QMS
Step 2: Assess the Maturity of Your QMS
Step 3: Improve Your QMS
PTAG provides leading firms in the Power, Oil & Gas, Petrochemical, Mining, and Capital Infrastructure markets with qualified People, efficient Business Processes, and Information Management Systems that ensure consistently successful delivery and efficient operation of major capital projects.
This site uses cookies. By continuing to browse the site, you are agreeing to our use of cookies.
Accept settingsHide notification onlyWe may request cookies to be set on your device. We use cookies to let us know when you visit our websites, how you interact with us, to enrich your user experience, and to customize your relationship with our website.
Click on the different category headings to find out more. You can also change some of your preferences. Note that blocking some types of cookies may impact your experience on our websites and the services we are able to offer.
These cookies are strictly necessary to provide you with services available through our website and to use some of its features.
Because these cookies are strictly necessary to deliver the website, refuseing them will have impact how our site functions. You always can block or delete cookies by changing your browser settings and force blocking all cookies on this website. But this will always prompt you to accept/refuse cookies when revisiting our site.
We fully respect if you want to refuse cookies but to avoid asking you again and again kindly allow us to store a cookie for that. You are free to opt out any time or opt in for other cookies to get a better experience. If you refuse cookies we will remove all set cookies in our domain.
We provide you with a list of stored cookies on your computer in our domain so you can check what we stored. Due to security reasons we are not able to show or modify cookies from other domains. You can check these in your browser security settings.
These cookies collect information that is used either in aggregate form to help us understand how our website is being used or how effective our marketing campaigns are, or to help us customize our website and application for you in order to enhance your experience.
If you do not want that we track your visit to our site you can disable tracking in your browser here:
We also use different external services like Google Webfonts, Google Maps, and external Video providers. Since these providers may collect personal data like your IP address we allow you to block them here. Please be aware that this might heavily reduce the functionality and appearance of our site. Changes will take effect once you reload the page.
Google Webfont Settings:
Google Map Settings:
Google reCaptcha Settings:
Vimeo and Youtube video embeds:
The following cookies are also needed - You can choose if you want to allow them:
You can read about our cookies and privacy settings in detail on our Privacy Policy Page.
Privacy Policy